AI Commitments Monitor
Meta, Alphabet, Microsoft, Oracle and Amazon have signed $3,062B of AI infrastructure deals that have not been delivered yet.
$3.1 Trillion signed by Meta, Alphabet, Microsoft, Oracle and Amazon, not yet delivered
- → The monitor
- → What these quantities are
- → Implied committed rates
- → Hyperscaler Bonds: the $392.8B of bonds these five companies have sold since January 2025
- Debt, at face value$559B
- Leases already started$312B Finance leases $98B · operating leases $214B
- Data center leases signed, not yet started$1,304B
- Contracts to buy chips, power and capacity$1,758B
Meta's latest filing does not disclose finance-lease liabilities, so the finance figure leaves Meta out.
§ The monitor
| Company | Leases not yet commenced | Purchase & other commitments | All-in obligations | Revenue backlog (RPO) | Support instruments |
|---|---|---|---|---|---|
| Meta 10-Q Q3 2026 (period 2026-09-30), acc 0001628280-26-066773 | $355.7B Sep-26 +76.7 vs Jun-26 ($279B) data centers, energy-related infrastructure, colocations, network infrastructure; commencing 2026 to 2036, terms >1 to 30 yrs | $454.5B Sep-26 +105.2 vs Jun-26 ($349.3B) non-cancelable, mostly third-party cloud capacity, servers and network, energy services; ~$45.85B due rest of 2026, ~$121.41B due 2027; excludes $14.72B contingent cloud capacity; $10.8B of money-market funds escrowed against multi-year infrastructure purchase agreements (released 2028 to 2030) | $925B Sep-26 leases started: finance not disclosed · operating $31.2B debt = $84.0B face (carrying $83.67B); balance-sheet operating lease liabilities $31.17B; finance-lease liabilities not disclosed in the Q3 10-Q (fin-lease ROU assets $11.70B), so the all-in stack is understated by that amount | — no compute revenue backlog | $41.5B Sep-26 maximum RVG, unconsolidated Louisiana and Texas (El Paso) ventures, 20% interest each (no liability recorded; payments 'not probable'; max exposure $68.4B). Texas venture formed Jul-26; its lease commences 2028, Louisiana 2029 |
| Alphabet 10-Q Q3 2026 (period 2026-09-30), acc 0001652044-26-000084 | $130.5B Sep-26 +45.3 vs Jun-26 ($85.2B) data centers and energy infrastructure; commencing 2026–2031, terms 1–26 yrs; separately, a short-term lease signed Jun-26 and amended Sep-26, ~$6.0B remaining non-cancelable, now in short-term lease cost | $802.1B Sep-26 note-level supply + energy + content commitments, incl. $4.5B of standby letters of credit. New basis in Q3: supply contracts with a price and volume range are stated at their maximum contractual limits (Q2 counted $707.0B 'fixed or guaranteed'), so no like-for-like delta. Supply contracts run through 2032, energy take-or-pay through 2054. Excludes $122.3B of open purchase orders (MD&A total incl. them $924.4B; $213.4B due within 12 months) | $1,084B Sep-26 backlog ÷ all-in: 0.52× leases started: finance $3.7B · operating $20.5B debt = $127.49B total face incl current portion; op leases $20.51B + fin leases $3.71B; a $5.0B Waymo secured term loan signed Oct-26 is not guaranteed by Alphabet and is not in the face total | $567.7B Sep-26 +48.2 vs Jun-26 ($519.5B) $560.8B Google Cloud; just over 55% expected within 24 months; definition includes ≤1-yr contracts since Q1-26; includes $16.8B from a multi-year agreement with Crux AI, a related-party joint venture with Blackstone; 'limited number' of TPU-system supply agreements began recognizing revenue in Q2-26, significant majority expected in 2027 | $48B Sep-26 data-center backstops as credit derivatives, notional (was $43.8B Jun-26, $28.4B Mar-26, $16.9B Dec-25, $0 Dec-24); fair-value liability $606M, $1.26 per $100 of notional (Jun-26 $1.86); a further $27.7B of backstops to be put in place, $10.0B of it with Crux AI; separately $16.2B of energy-equipment guarantees (terms through Jan-2049), a $6.6B maximum exposure to repurchase previously sold TPU hardware, and a $20.0B milestone-contingent funding commitment to an unnamed private company, booked as an equity derivative |
| Microsoft 10-Q Q1 FY2027 (period 2026-09-30), acc 0001193125-26-436133 | $364.6B Sep-26 +35.5 vs Jun-26 ($329.1B) primarily datacenters; commencing FY2027–FY2034, terms 1–20 yrs; some arrangements subject to contractual conditions being met | $194.1B Jun-26 +52.0 vs Jun-25 ($142.1B) the Q1 FY27 10-Q restates no purchase or construction figure, so Jun-26 stands. $194.06B purchase commitments (datacenter take-or-pay + open POs, not split out; $169.0B due FY27). Separately disclosed: $34.57B construction commitments, excluded from the normalized columns because only Microsoft discloses construction as its own line; the prior-year row ($142.05B) included it, so the delta is mixed-basis. At Sep-26: $35.7B of receivables tied to facilitating server-component purchases (Jun-26 $27.8B) and $12.6B of investments restricted under a supplier agreement (Jun-26 $11.3B) | $698B Sep-26 backlog ÷ all-in: 0.97× leases started: finance $71B · operating $27.5B debt = $41.27B total face value ($4.85B repaid in the quarter); op leases $27.48B + fin leases $70.97B; after the quarter: $25.0B of notes in ten series, settling Nov 4, 2026 and not in the face total (maturities 2028–2066; eight fixed at 4.850%–6.350%, two floating at Compounded SOFR + 0.35% and + 0.53%; FWP acc 0001193125-26-439794) | $683B Sep-26 −1.0 vs Jun-26 ($684B) $677B commercial (+73% y/y), weighted-avg duration ~2.3 yrs, ~30% recognized within 12 mo; backlog ÷ all-in ratio uses the commercial figure (house basis) | none disclosed as a separate category; related: $13.0B OpenAI funding commitment, $12.0B funded at Sep-26 |
| Oracle 10-Q FY27 Q1 (period 2026-08-31), acc 0001193125-26-389274 | $288B Aug-26 +28.0 vs May-26 ($260B) terms 15–19 yrs, generally commencing Q2 FY27–FY29, substantially all data-center arrangements (10-Q, Aug-26; $260B at May-26; $4.1B at May-22); the May-26 10-K adds that one lease carries a $3.3B guarantee of the lessor's borrowing (matures Sep-26) | $34.2B Aug-26 +20.8 vs May-26 ($13.3B) unconditional purchase and other obligations with terms of one year or more: cloud-infrastructure component supply and data-center power; the $19B signed after the May year-end now sits inside the figure | $491B Aug-26 backlog ÷ all-in: 1.35× leases started: finance $9.2B · operating $34.6B debt = balance-sheet notes payable and other borrowings, current $7.63B + non-current $117.71B (carrying; the 10-Q carries no debt-note face table); op leases $34.62B + fin leases $9.19B; $3.1B repaid in the quarter | $664B Aug-26 +26.0 vs May-26 ($638B) ~13% expected to convert to revenue within 12 months, 37% in months 13-36, 34% in months 37-60; more than $30B of AI cloud contracts booked in the quarter; the issuer states the new contracts carry no incremental impact on its plans to raise capital | $3.3B May-26 guarantee of a lessor's borrowing within the lease pipeline |
| Amazon 10-Q Q3 2026 (period 2026-09-30), acc 0001018724-26-000040 | $164.9B Sep-26 +27.7 vs Jun-26 ($137.2B) $114.8B of the undiscounted total falls due after 2030; commencement dates and lease terms not disclosed | $273.4B Sep-26 +125.0 vs Jun-26 ($148.4B) $159.64B property and equipment (its own line from Q3; variable-price agreements counted at minimum pricing; $63.9B due 2027) + $94.76B other unconditional purchase obligations (energy, digital media content, software) + $18.99B other commitments; open purchase orders, generally cancelable, are excluded | $734B Sep-26 backlog ÷ all-in: 0.79× leases started: finance $14.5B · operating $100.3B debt = $180.89B total face incl current portion (adds Jul-26 $25.0B USD notes, Sep-26 £4.25B sterling notes, $17.5B term loan drawn Sep-26); op leases $100.29B + fin leases $14.50B; not drawn: a secured supplier Loan Facility of up to about $80.0B for technology infrastructure purchases (draws Q1-27 to Q3-28, five-year maturities, booked as long-term debt when drawn) | $578B Sep-26 +82.0 vs Jun-26 ($496B) AWS, contracts >1 yr, weighted-avg life 6.1 yrs (6.4 at Jun-26); named arrangements unchanged: OpenAI (existing $38.0B expanded by $100.0B over 8 yrs, Q1) and Anthropic (expanded by more than $100B over 10 yrs, Q2), both including obligations tied to the performance of AWS chips | none disclosed as backstop/guarantee; related: Anthropic financing facility of up to $20.0B, released at compute delivery milestones ($15.0B available); OpenAI $35.0B equity commitment fully funded (last $21.3B in Q3) |
$B, undiscounted, as disclosed. Windows differ where issuers' fiscal calendars and disclosure practices differ and are labeled on every cell. Deltas are shown only against the same issuer's prior disclosure of the same quantity. Oracle's prior lease figure is fiscal 2022, the earliest comparable disclosure. All-in obligations = the two forward columns plus debt at face value and balance-sheet lease liabilities (operating + finance), each from the same issuer's cited filings. It is a total fixed-claims stack built only from components all five issuers disclose, computed by us from the disclosed figures. Construction commitments, disclosed only by Microsoft, are excluded from these columns. The backlog ÷ all-in ratio is a conservative screen, not a coverage finding: RPO is contracted revenue only, while debt and commenced leases are also serviced by revenue no backlog captures (advertising, retail, licenses). Support instruments are contingent and are in no total.
§ What these quantities are
Leases signed but not yet commenced are rental agreements on facilities, overwhelmingly data centers, that have not been delivered. Nothing appears on the balance sheet until the landlord hands over the building. At commencement, a lease liability and right-of-use asset are recognized. The footnote is therefore a forward calendar of balance-sheet lease liabilities, with terms disclosed as long as 30 years. Purchase and other commitments are contracts to buy goods and services (cloud capacity, chips and servers, power). Most issuers report the non-cancelable portion or contractual minimum, in their own language: "non-cancelable," "take-or-pay," "unconditional… enforceable and legally binding." Alphabet's long-term supply contracts allow a range of price and volume. From its Q3 2026 10-Q, Alphabet states them at the maximum of that range. Its row shows that note-level figure and lists its open purchase orders in the note, outside the column. Microsoft does not report its open purchase orders separately, so its figure includes them. Remaining performance obligations are the same class of contract seen from the seller's side: contracted future revenue not yet recognized. Support instruments are credit support written around other parties' financings: payment backstops (Alphabet accounts for these as credit derivatives at fair value), residual value guarantees, and guarantees of lessors' borrowings.
Why a compute-credit record tracks them: these commitments are the collateral of the offtake-backed lane of the compute credit tracker. A compute provider's contracted cash flows from an investment-grade customer are that customer's purchase commitment seen from the other end, and the market prices their quality. The launch analysis, with the full decomposition, conditionality language, and counterparty detail, is Breaking Down Big Tech's $1.65 Trillion "Hidden Debt". On the support-instruments column specifically, see How Alphabet Pays to Obtain Compute Capacity at Speed: the backstop book and its booked cost per $100, which this monitor updates with each Alphabet 10-Q.
Sources: latest and prior filings per issuer as listed in each row, verified against the documents on EDGAR. This page is updated within days of each new 10-Q/10-K from the covered issuers. Figures are as-disclosed and are not restated between filings. Nothing here is a solvency opinion, a forecast, or investment advice.
§ Implied committed rates
Where a publicly disclosed multi-year compute deal states enough (dollars, term, and quantity), CCIR backs out the implied unit rate. Every figure is implied, computed by CCIR from the disclosed figures, and graded by disclosure quality. None is an observed price. These rows are not part of any CCIR daily rate series. The methodology and per-deal detail are in the research note Implied Committed Rates. This table updates as deals publish.
Assumptions, permanent: ratable spend across the disclosed term; 100% of contracted hours billed; all disclosed dollars treated as compute; constant fleet; 8,760 hr/yr. Every assumption biases the implied rate downward: all figures are floors on blended committed rates, not observed prices. Grades: A = dollars, term, and units all company-disclosed; B = one input from attributed press. Grade-C rows (talks-stage or heavy estimation) do not publish. $/GPU-hr and $/MW-month rows are never blended. Chip column = the generation as the parties disclosed it. Where unspecified, the rate is fleet-blended. No performance adjustment across generations: rates on different chips are different products, not comparable prices. This table carries $/GPU-hr rows only, newest first; megawatt-basis reads (IREN's grade-A basis, Stargate) live in the research note.
| Deal | Chip | Disclosed | Implied rate | Grade | As of |
|---|---|---|---|---|---|
| Anthropic–xAI (SpaceX) | unspecified | $1.25B/mo through May 2029 · ~325,000 NVIDIA GPUs · 90-day outs after initial 3 mo | $5.27/GPU-hr | A | Jun-26 |
| Microsoft–IREN | GB300 | $9.7B · 5 yr · 200MW critical IT load | ~$2.2/GPU-hr (CCIR density estimate) | A (MW) | Nov-25 |
| OpenAI–AWS | GB200/GB300 | $38B · 7 yr · "hundreds of thousands" of GPUs + CPUs | $1.24–3.10/GPU-hr (band) | B | Nov-25 |
| Microsoft–Nscale/Aker (Narvik) | GB300 | $6.2B · 5 yr · ~52,000 GPUs | $2.72/GPU-hr | A | Sep-25 |
| Microsoft–Nebius | GB300 (press) | $17.4B (up to $19.4B) · 5 yr · ">100k" GPUs per press | $3.97/GPU-hr | B | Sep-25 |
Not computable, no rate published: Meta–CoreWeave (~$35.2B total, no units disclosed), OpenAI–CoreWeave (~$22.4B, no units), Anthropic–Microsoft Azure ($30B, no term; the "up to 1GW" is a separate additional commitment and is not a valid denominator). Sources and per-row caveats in the research note.